Case study / Delivery record
Adobe Commerce upgrade go-lives for a Southeast Asian sports-retail group
As the delivery lead, I governed Adobe Commerce 2.4.8 upgrades for three Southeast Asian sports-retail brands. Formal acceptance and BAST handover protected live trading while leaving each client team ready to operate the platform.
- 3 sports-retail brands upgraded
- Adobe Commerce 2.4.8
- zero-downtime cutover
- formal UAT across 3 storefronts
- 3 signed BAST handovers
01
Context
Three live storefronts were due for platform upgrades.
A regional retail group operating global footwear and sportswear brands on Adobe Commerce, due for platform upgrades across three storefronts.
02
Challenge
Acceptance and handover mattered as much as the cutover.
Upgrade live stores with minimal downtime, formal acceptance, and clean handover to the client’s BAU team.
03
What I did
Release governance connected UAT to business-as-usual ownership.
Ran go-live governance end to end: UAT workbooks, go-live approval workflows, release notes, post-launch monitoring and formal handover (BAST) documents per brand.
04
Outcome
Three brands went live with signed operational handovers.
Three production upgrades delivered with minimal downtime and signed handovers; BAU ticket tracking in place from day one.
05
What it taught me
The handover document is part of the product.
The handover document is the product. If the client cannot run it without you, you have not finished.
- 01
Upgrade planning
- 02
Formal UAT
- 03
Release approval
- 04
Three cutovers
- 05
BAST handover
Questions about this engagement
Frequently asked questions
What was upgraded in this engagement?
Three Southeast Asian sports-retail storefronts were upgraded to Adobe Commerce 2.4.8 for a regional retail group operating global footwear and sportswear brands.
How do you upgrade a live Adobe Commerce store with minimal downtime?
Audit extensions and customisations for compatibility, rehearse the full cutover in staging with a timed runbook, test the rollback, agree a go/no-go checkpoint with the client, and run a defined hypercare period after launch.
What is a BAST handover?
BAST (Berita Acara Serah Terima) is the Indonesian formal handover and acceptance document. Each brand signed one at the end of the upgrade, confirming acceptance and transferring operation to the client's business-as-usual team.